Trains That Make Up Lost Time, 26 Oct to 8 Nov 2026

The 15 trains that made up the most time per run in our own delay history, 26 October to 8 November 2026, with method notes and the caveats that apply.

Aerial view of a bustling street in India with iconic yellow taxis and bustling pedestrians.

Photo: Nifty Highness / Pexels

Between 26 October and 8 November 2026, these 15 trains made up the most time per run in our own delay history. Recovery only happens after a train has fallen behind, so a high figure reflects a train that had fallen well behind. On no observed day was any of the 15 within 15 minutes of schedule.

How we measured it

The window covers 14 days, from 26 October to 8 November 2026. For each train and each day, we took the largest delay reported during that day's run, in minutes. A run counts as on time if that largest delay was within 15 minutes. Recovered time is the average number of minutes a train made up per run, from the same tracking data.

Of 6,884 trains in scope, 5,680 were ranked. Across all runs, the average largest delay was 61 minutes and 38% of runs were on time. These figures come from our own tracking of live running status. They are not an official statistic from Indian Railways, and they cover only the trains and days our tracker recorded.

The 15 trains

Ranked by average minutes recovered per run. Each train name links to its live status and history page.

TrainRouteAvg largest delay (min)Avg recovered (min)Days observed
12130 Azad HIND ExpressHowrah Jn to Pune Jn46235514
12809 Howrah MailC Shivaji Maharaj T to Howrah Jn31627114
54075 Be-dli PassengerBareilly to Delhi Jn39722913
12860 Gitanjali ExpressHowrah Jn to C Shivaji Maharaj T26921314
18477 Utkal ExpressPuri to Yog Nagari Rishikesh25020512
18029 LTT Shalimar ExpressLokmanya Tilak T to Shalimar21819814
11273 ET PCOI ExpressItarsi Jn to Prayagraj Chheoki26118714
12859 Gitanjali ExpressC Shivaji Maharaj T to Howrah Jn27918614
12716 Sachkhand ExpressAmritsar to Nanded44417714
12129 Azad HIND ExpressPune Jn to Howrah Jn33117614
12833 ADI HWH ExpressAhmedabad Jn to Howrah Jn24316214
02570 NDLS DBG SF SpecialNew Delhi to Darbhanga Jn30216214
04061 BGP ANVT SpecialBhagalpur to Anand Vihar Terminal24716114
11048 GKP DR ExpressGorakhpur Jn to Dadar25615813
01449 PUNE DNR SpecialPune Jn to Danapur36415214

What stands out

The Azad HIND Express (12130) from Howrah Junction to Pune Junction recovered an average of 355 minutes per run. Its average largest delay was 462 minutes, its median was 430 minutes, and its worst day reached 691 minutes. It was observed on all 14 days and was never within 15 minutes.

The Sachkhand Express (12716) had the highest median largest delay of the 15, at 476 minutes, yet it recovered 177 minutes per run on average. A large recovery figure does not mean a train was near schedule.

The Utkal Express (18477), which runs from Puri to Yog Nagari Rishikesh, is the only train in the table with cancelled days. It was cancelled on 2 of the 14 days and observed on the other 12. The Be-dli Passenger (54075) and the GKP DR Express (11048) were each observed on 13 of the 14 days.

What this means for travellers

  • Do not plan on recovery. Every train in this table was outside the 15-minute window on each observed day. Build a generous buffer into any connection or pickup.
  • Check the day, not the timetable. Look up the train's live running status on the morning of travel before you leave for the station.
  • Compare alternatives. If a connection is tight, the trip planner shows other trains and two-train options on the same route.
  • Read the trend, not one day. Our most delayed trains report covers the week before this window, and the earlier recovery report covers 26 September to 9 October.

Other apps may show a different delay for the same train on the same day. Our figures are only comparable with other figures from our own tracking. See why apps show different delay for the same train.

Live running status

Where is your train right now?

Live position, expected arrival at every stop and the delay history of the last few weeks.

Use it on your trip

Frequently asked questions

What does the largest delay during each day's run mean?

For each train and each day, we record the biggest delay the train showed during that day's run and use that figure. It is a peak across the run, not the delay at one station, so a train can have a large peak and still finish closer to schedule.

What counts as on time in this report?

A run counts as on time when its largest delay for the day was within 15 minutes. On-time rates in this report show the share of runs that met that test across the 14 days.

Is this official Indian Railways data?

No. These figures come from our own tracking of live running status over 26 October to 8 November 2026. They are useful for seeing patterns, but they are not an official punctuality statistic.

Can I rely on these trains to reach on time?

No. Each train in the table showed a large delay on most or all observed days, even though it recovered time during the run. Check the live status on the day of travel and leave a buffer for any connection.